Wastewater & Sewage Treatment Plant
JELUTONG SEWAGE TREATMENT WORKS
The Project comprises the construction and erection, completion, operation and maintenance of a sewage treatment plant (STP) catering for a population equivalent (PE) of 1.2 million for Georgetown, Penang.
LOCATION
Jelutong, Penang
CLIENT
Kementerian Tenaga, Air dan Komunikasi
COMPLETION DATE
2007
DETAIL WORKS INCLUDED
• Main inlet pump station
• Effluent disinfection channel and outfall
• Digester equipment building
• Main inlet substation building
• TNB substation and generator set building
• Common utilities trench
• C&S infras
• Sludge holding tank
• Anaerobic digester tank
• Reclaimed effluent pump station
• Administration building
• Guard house
• Scada System & Instrumentation
• Sequential batch reactor
• Gas holding tank
• Centralised sludge storage buildings
• Vehicle depot and maintenance workshop
• Refuse chamber
• M&E works
SERVICES PROVIDED
• Planning and Detailed Design
• Contract Administration
• Design Management
• Construction Supervision
BUNUS PHASE 2 CENTRALIZED SEWAGE TREATMENT PLANT
LOCATION
Kuala Lumpur
CLIENT
Ekovest-MRCB JV Sdn Bhd
COMPLETION DATE
2018
DETAIL WORKS INCLUDED
• Preliminary treatment works
• Tertiary treatment building
• Anaerobic digester tank
• Gas storage tanks
• Administration building
• Guard house
• M&E works
• Sequential batch reactor
• Sludge holding tank
• Digester equipment building
• Gas flare
• Odour removal system
• Filtrate / chemical house
• C&S infrastructural works
• SBR blower house
• Sludge treatment building
• Biogas Genset Room
• Sludge cake yard
• TNB substation
• SCADA System & Instrumentation
SERVICES PROVIDED
• Detailed design
• Contract administration
• Authority submission
• Construction supervision
PEMBINAAN LOJI RAWATAN KUMBAHAN SERANTAU DAN RANGKAIAN PAIP PEMBETUNGAN DI BANDAR KUANTAN, PAHANG (REKA DAN BINA)
LOCATION
Bandar Kuantan, Pahang
CLIENT
Jalur Cahaya Sdn Bhd
COMPLETION DATE
Current
DETAIL WORKS INCLUDED
• Extended Aeration (EA) treatment system
• The effluent quality to comply Standard A as per MSIG
• Design of treatment process, structure, geotechnical and M&E
• Centralised Sewage Treatment Plant (CSTP) designed for the capacity of 200,000 Population Equivalent (PE) for Phase 1 (ultimate 400,000 PE)
SERVICES PROVIDED
• Planning
• Contract Administration
•Design Review
• Construction Supervision
BAYAN BARU SEWAGE TREATMENT WORKS
The Project comprises the construction and erection, completion, operation and maintenance of a sewage treatment plan (STP) catering for a population equivalent (PE) of 400,000 for Bayan Baru, to replace the two (2) existing oxidation ponds.
LOCATION
Bayan Baru, Penang, Malaysia
CLIENT
Sewerage Services Department, Ministry of Housing And Local Government
COMPLETION DATE
2003
DETAIL WORKS INCLUDED
• Main inlet pump station
• Clarifier
• Surplus activated sludge tank
• Tank reception facilities
• Administration building & maintenance workshop
• Preliminary treatment tank
• Effluent collection chamber and outfall
• RAS/SAS sludge pump station
• Reclaimed effluent pump station
• Sludge thickening and dewatering buildings
• Modified oxidation ditch
• Chlorine contact tank
• Electrical substations
• Sludge storage tank and building
SERVICES PROVIDED
• Planning and Detailed Design
• Design Management
• Project Management
• Construction Supervision
• Programme Management
• Contract Administration
INTEGRATED SEWERAGE PROJECT IN PUTRAJAYA, MALAYSIA
The development of the wastewater system for Putrajaya comprises of modern water-borne sewage collection system with lifting stations and centralized sewage treatment plants (STP). Two sites for the STP have been identified; one to the north-east of the proposed development for STP1 with 75,000 P.E. and the other south for STP2 with 600,000 P.E.
LOCATION
Putrajaya Federal Government Administrative Centre for Malaysia
CLIENT
Putrajaya Holdings Sdn Bhd
COMPLETION DATE
2000
DETAIL WORKS INCLUDED
• Sewage Treatment Plant No. 1
(75,000 P.E.)
• Sewage Treatment Plant No. 2
(600,000 P.E.)
• Sewage Switching Plant and
Pumping Stations (18 nos)
• Sewage Collection Systems
( 90km of Trunk Sewer network system)
SERVICES PROVIDED
• Sewerage Master Plan Study
• Construction Supervision
• QA/QC
• Conceptual Design
• Project Management
• Programme Management
• Detailed Design
• Construction Management
• Project Commissioning
PUTRAJAYA WASTEWATER DEVELOPMENT PROJECTS
The project involves feasibility, concept and detailed design of the Overall Sewerage System for Putrajaya with a development area of approximately 4950 ha. The project is implemented in phases between year 1996 to year 2010. The sewerage Development includes the laying of trunk sewers up to 2100mm diameter in size, construction of 15 numbers of sewage pumping stations with capacity of up to 250,000PE, two(2) numbers of Sewage Treatment Plant of capacity 100,000PE and 600,000PE), force mains of size up to 1000mm in diameter.
LOCATION
Putrajaya,Wilayah Persekutuan Malaysia
CLIENT
Putrajaya Holdings Sdn Bhd
COMPLETION DATE
2012
DETAIL WORKS INCLUDED
• SCADA control and instrumentation
• Preliminary and detailed design of sewerage system-pump station, pipeline, treatment plants etc.
• Hydraulic analysis
• Site survey and geotechnical investigation
• Formulation, evaluation and assessment of overall catchment planning
• Odour control
• Sludge treatment
• Emergency Response Plans for Pump Stations
SERVICES PROVIDED
Master Planning, Detailed Design and Supervision of Construction for Sewerage Works as follows:-
• Sewers
• Pump Stations
• SCADA and PLC control
• Sewage Treatment Plants
• Pumping equipment and ancillary works
YEN SO SEWAGE TREATMENT WORKS
Yen So STP is designed for the capacity of 200,000m3/day or (900,000PE), treating sewage generated from Kim Nguu and Set River Catchments and Yen So Development to equal or better than discharge standard TCVN 2005 – 5945.
LOCATION
Hanoi, Vitenam
CLIENT
Gamuda Land Vietnam
COMPLETION DATE
2010
DETAIL WORKS INCLUDED
• River Barrage
• Sequential batch reactor
• Gas holding tank
• Digester equipment building
• Vehicle depot and maintenance workshop
• Refuse chamber
• C&S infrastructural works
• Main inlet pump station
• Effluent disinfection channel and outfall
• Reclaimed effluent pump station
• Main inlet substation building
• Substation and generator set building
• Scada System & Instrumentation
• Sludge holding tank
• Anaerobic digester tank
• Centralised sludge storage buildings
• Administration building
• Guard house
• M&E works
SERVICES PROVIDED
• Planning and Detailed Design
• Construction Supervision
• Design Management
• Contract Administration
INTEGRATED SEWERAGE PROJECT FOR KOTA KINABALU, SABAH
Kota Kinabalu has been experiencing dynamic growth in the last decades. The Sabah State Government recognise the urgent need for the provision of centralised sewerage system required for improving the environment and living conditions of the people; has launched a project to centralise and upgrade the existing sewerage systems for Central Catchment and Southern Catchment in Kota Kinabalu
Central Catchment covers a total land area of approximately 6,063 hectares with the projected population equivalent (PE) of 200,000 up to year 2020. The scope of works for Central Catchment is to provide a sewerage network of pumping stations and sewers conveying flows to existing Regional Sewage Treatment Plant (RSTP) in Inanam. The Phase 1 sewerage works for Central Catchment involves laying of 15km of sewers and upgrading the existing RSTP to cater the flows subsequently.
Southern Catchment covers a total land area of approximately 5,106 hectares with the projected population equivalent (PE) of 355,380 up to year 2020. The scope of works for Southern Catchment is to provide a sewerage network of pumping stations and sewers conveying flows to a new Regional Sewage Treatment Plant in Penampang. The Phase 1 sewerage works for Southern Catchment involves construction of 10km of sewers and building a new RSTP in Penampang.
LOCATION
Kota Kinabalu, Sabah, Malaysia
CLIENT
Jabatan Kerja Raya, Sabah
COMPLETION DATE
2010
DETAIL WORKS INCLUDED
• New Sewage Pumping Stations (2 nos)
• Sewage Collection Systems (25km of Trunk Sewer)
• Refurbishment of existing Pumping Stations (8 nos)
• Upgrading existing Sewage Treatment Plant at Inanam
• Decommissioning of existing Pumping Stations and Sewage Treatment Plants
• New Sewage Treatment Plant in Penampang (ultimate 300,000 PE, 75,000 PE for Phase 1)
SERVICES PROVIDED
• Sewerage Master Plan Study
• Construction Supervision
• Conceptual Design
• Contract Administration
• Detailed Design
CYBERJAYA WASTEWATER PROJECT
The project involved conceptual and detailed design under the design and build concept of two units of sewage pump stations for Cyberjaya with a development area of approximately 7,000 ha. The scope of works includes the laying of sewer force mains 600mm and 1,000 mm diameter in sizes, construction of 2 numbers of sewage pumping stations with capacity of 74,500PE (PS4), and 290,000 PE (PS2-9).
LOCATION
Cyberjaya, Malaysia
CLIENT
Setia Hauruman Sdn Bhd
COMPLETION DATE
2007
DETAIL WORKS INCLUDED
• Odour control
• Hydraulic computation
• Site survey and geological investigation
• Formulation, evaluation and assessment of
overall catchment planning
• Preliminary and detailed design of sewerage
system- Pump station, pipeline, and etc.
SERVICES PROVIDED
• Conceptual and Detailed Design
• Construction Supervision
GENTING HIGHLANDS 60,000 PE SEWAGE TREATMENT PLANT
The Project comprises the construction and erection, completion, operation and maintenance of a new sewage treatment plan (STP) catering for an additional population equivalent (PE) of 60,000 as extension to the existing sewage treatment plant for Genting Highlands First World Hotel.
LOCATION
Genting Highlands, Pahang, Malaysia
CLIENT
Resorts World Bhd
COMPLETION DATE
2008
DETAIL WORKS INCLUDED
• Inlet screening chamber
• Two modules of Sequencing Batch Reactor (SBR) tanks
• Sludge thickening and dewatering building
• Supervisory Control and Data Acquisition (SCADA) for semi-automated monitoring and process controlling
• Grit chamber
• Surplus activated sludge tank
• RAS/SAS sludge pump station
• Odour removal system
• Administration building & maintenance workshop
• Grease chamber
• Chlorination tank
• Electrical substation
• Reclaimed effluent pump station
• Sludge storage tank and building
SERVICES PROVIDED
• Planning and Detailed Design
• Design Management
• Project Management
• Construction Supervision
• Programme Management
• Contract Administration
JAYA ONE STP & WASTEWATER TREATMENT
Review & Upgrade of the Performance of Odour Control System of Jaya One STP.
LOCATION
Selangor
CLIENT
Tetap Tiara Sdb Bhd
COMPLETION DATE
2014
DETAIL WORKS INCLUDED
• Air Sampling & Analysis
• Oil & Grease Removal Facility for Wastewater
• Review and Upgrade of STP (including Wastewater Characteristics Study)
SERVICES PROVIDED
• Review & upgrade existing plant
• Design & build
FEASIBILITY STUDY OF CONSTRUCTED WETLANDS FOR SEWAGE TREATMENT
LOCATION
Puchong, Selangor
CLIENT
NAHRIM
COMPLETION DATE
2021
DETAIL WORKS INCLUDED
• Produce preliminary design
• Cost estimation of constructed wetland for sewage treatment
• Conduct feasibility study for constructed wetland for sewage treatment
• Collect and analyse information from previous flood reports, site investigation
SERVICES PROVIDED
• Data collection
• Site investigation detailed design
• Cost estimation
INDUSTRIAL WASTEWATER TREATMENT PLANT, W.R GRACE SPECIALTY CHEMICALS (M) SDN. BHD. (GRACE), PAHANG
Alternative Analysis (FEL 1) for ammonical nitrogen (AN) treatment technologies to comply with Standard B of Environmental Quality Act (EQA) 1974: Environmental Quality (Industrial Effluent) Regulation 2009.
Sampling and compositional analysis for wastewater, budgetary cost estimates, risk management overview, project execution plan.
LOCATION
Pahang
CLIENT
W.R GRACE SPECIALTY CHEMICALS (M) SDN. BHD.
COMPLETION DATE
2020
DETAIL WORKS INCLUDED
• Project execution plan
• Budgetary cost estimates
• Risk management overview
• Sampling and compositional analysis for wastewater
• Alternative Analysis (FEL 1) for ammonical nitrogen (AN) treatment technologies to comply with Standard B of Environmental Quality Act (EQA) 1974: Environmental Quality (Industrial Effluent) Regulation 2009
SERVICES PROVIDED
Option Analysis & FEL1 Report
MAS INDUSTRIAL WASTEWATER TREATMENT PLANT
Centralised Industrial Wastewater Treatment Plant for metal and oil bearing effluent, sludge storage design, tender specifications, site supervision, project management & testing/commissioning.
LOCATION
Subang International Airport, Malaysia
CLIENT
Malaysia Airlines
COMPLETION DATE
1994
DETAIL WORKS INCLUDED
• Sludge storage design
• Testing and commissioning of the wastewater treatment plant
• Centralised Industrial Wastewater Treatment Plant for metal and oil bearing effluent
SERVICES PROVIDED
• Detailed design
• Contract administration
• Authority submission
• Construction supervision
Integrated Management System
&
Quality Policy
MS ISO 9001:2015 Quality Management Systems
MS ISO 14001:2015 Environmental Management System
MS ISO 45001:2018 Occupational Health and Safety Management System