Dams
BEKOK DAM, JOHOR, MALAYSIA
This Project is an earthfill dam measuring 16m high x 860m long with spillway, regulating outlet stilling basin, discharge channel and auxiliary spillway
LOCATION
Bekok Dam, Negeri Johor
CLIENT
Jabatan Pengairan dan Saliran, Malaysia
COMPLETION DATE
1991
DETAIL WORKS INCLUDED
• Earth fill dam with spillway
• Associated structures such as pumping station, access road and intakes
• Regulation outlet
• Auxiliary spillway
• Stilling basin
• Discharge channel
SERVICES PROVIDED
• Geotechnical investigation & survey
• Environmental impact assessment
• Bid Evaluation
• Hydrology & hydraulic studies
• Detailed design
• Construction Supervision
• Water resources studies
• Contract Documentation
• Testing, Commissioning & Handing Over
SG. KELINCHI DAM, TRANSFER TUNNEL, PUMPING STATION & ASSOCIATED WORKS
The Project is an inter-basin transfer of water from Upper Muar catchment to Sg. Terip for augmenting water supply to the 2 districts of Seremban and Port Dickson.
LOCATION
Upper Muar River Basin, Kuala Pilah District, Negeri Sembilan
CLIENT
Jabatan Bekalan Air, Negeri Sembilan
COMPLETION DATE
1999
DETAIL WORKS INCLUDED
• 54m high x 554m length secondary dam
• 56m high multi-level draw-off RC tower
• 2.7m nominal diameter tunnel for 6.2km length
• 70m high x 270m length modified homogeneous embankment
• Associated structures such as pumping station, access road and intakes
SERVICES PROVIDED
• Geotechnical investigation & survey
• Environmental impact assessment
• Bid Evaluation
• Hydrology & hydraulic studies
• Detailed design
• Construction Supervision
• Water resources studies
• Contract Documentation
• Testing, Commissioning & Handing Over
KAJIAN KEJURUTERAAN SISTEM BEKALAN AIR EMPANGAN BATU HAMPAR, REMBAU, NEGERI SEMBILAN
The project consists of a 50m high dam at Sg. Batu Hampar with a storage volume of 2.5 million m3 and a 30m wide barrage at Sg. Rembau to enable abstraction of 100 MLD to meet the water supply requirements up to year 2020 for domestic and industrial uses in the districts of Rembau and Port Dickson (South), Negeri Sembilan.
LOCATION
Negeri Sembilan
CLIENT
Jabatan Bekalan Air, Negeri Sembilan
COMPLETION DATE
2010
DETAIL WORKS INCLUDED
• Assessment of proposed Sg. Batu Hampar Dam and Sg. Rembau Barrage
• Feasibility study of proposed water supply system including hydrological modelling for Sg. Rembau Intake
• Conceptual Design of RCC Dam, 100 MLD Water Treatment Plant, Pump House, Intake, Barrange, Reservoirs and Pipelines
• Water demand analysis and projection of water demand to meet the residential, institutional, commercial and industrial supply
SERVICES PROVIDED
• Preliminary environmental impact assessment
• Detailed engineering investigation
• Conceptual design
Integrated Management System
&
Quality Policy
MS ISO 9001:2015 Quality Management Systems
MS ISO 14001:2015 Environmental Management System
MS ISO 45001:2018 Occupational Health and Safety Management System