Sewerage Network System
CYBERJAYA WASTEWATER PROJECT
The project involved conceptual and detailed design under the design and build concept of two units of sewage pump stations for Cyberjaya with a development area of approximately 7,000 ha. The project is implemented in phases. The scope of works includes the laying of sewer force mains 600mm and 1000 mm diameter in sizes, construction of 2 numbers of sewage pumping stations with capacity of 74,500PE (PS4), and 290,000 PE (PS2-9).
LOCATION
Cyberjaya, Malaysia
CLIENT
Setia Hauruman Sdn Bhd
COMPLETION DATE
2007
DETAIL WORKS INCLUDED
• Formulation, evaluation and assessment of overall catchment planning
• Odour control
• Sewerage system-Pump station, pipeline & etc.
• Hydraulic computation
• Site survey and geological investigation
SERVICES PROVIDED
• Preliminary design
• Detailed design
INTEGRATED SEWERAGE PROJECT FOR KOTA KINABALU, SABAH
Kota Kinabalu has been experiencing dynamic growth in the last decades. The Sabah State Government recognise the urgent need for the provision of centralised sewerage system required for improving the environment and living conditions of the people; has launched a project to centralise and upgrade the existing sewerage systems for Central Catchment and Southern Catchment in Kota Kinabalu
Central Catchment covers a total land area of approximately 6,063 hectares with the projected population equivalent (PE) of 200,000 up to year 2020. Southern Catchment covers a total land area of approximately 5,106 hectares with the projected population equivalent (PE) of 355,380 up to year 2020.
LOCATION
Kota Kinabalu, Sabah, Malaysia
CLIENT
Jabatan Kerja Raya, Sabah
COMPLETION DATE
2010
DETAIL WORKS INCLUDED
• New Sewage Pumping Stations (2 nos)
• Sewage Collection Systems (25km of Trunk Sewer)
• Refurbishment of existing Pumping Stations (8 nos)
• Upgrading existing Sewage Treatment Plant at Inanam
• Decommissioning of existing Pumping Stations and Sewage Treatment Plants
• New Sewage Treatment Plant in Penampang
(ultimate 300,000 PE, 75,000 PE for Phase 1)
SERVICES PROVIDED
• Sewerage Master Plan Study
• Construction Supervision
• Conceptual Design
• Contract Administration
• Detailed Design
PUTRAJAYA WASTEWATER DEVELOPMENT PROJECTS
The project involved feasibility, concept and detailed design of the Overall Sewerage System for Putrajaya with a development area of approximately 4,950 ha. The project is implemented in phases between year 1996 to year 2010. The sewerage development includes the laying of trunk sewers up to 2,100mm diameter in size, construction of 15 numbers of sewage pumping stations with capacity of up to 250,000PE, 2 numbers of Sewage Treatment Plant of capacity 100,000PE and 600,000PE, force mains of size up to 1,000mm in diameter.
LOCATION
Putrajaya,Wilayah Persekutuan Malaysia
CLIENT
Putrajaya Holdings Sdn Bhd
COMPLETION DATE
2012
DETAIL WORKS INCLUDED
• Preliminary and detailed design of sewerage system- pump station, pipeline, treatment plants etc.
• Formulation, evaluation and assessment of overall catchment planning
• Hydraulic analysis
• SCADA control and instrumentation
• Site survey and geotechnical investigation
• Sludge treatment
• Odour control
• Emergency Response Plans for Pump Stations
SERVICES PROVIDED
• Master Planning
• Detailed Design
• Construction Supervision
INTEGRATED SEWERAGE PROJECT IN PUTRAJAYA, MALAYSIA
The development of the wastewater system for Putrajaya comprises of modern water-borne sewage collection system with lifting stations and centralized sewage treatment plants (STP). Two sites for the STP have been identified; one to the north-east of the proposed development for STP1 with 75,000 P.E. and the other south for STP2 with 600,000 P.E.
LOCATION
Putrajaya Federal Government Administrative Centre for Malaysia
CLIENT
Putrajaya Holdings Sdn Bhd
COMPLETION DATE
Current
DETAIL WORKS INCLUDED
• Sewage Treatment Plant No. 1
(75,000 P.E.)
• Sewage Treatment Plant No. 2
(600,000 P.E.)
• Sewage Switching Plant and
Pumping Stations (18 nos)
• Sewage Collection Systems
( 90km of Trunk Sewer network system)
SERVICES PROVIDED
• Sewerage Master Plan Study
• Construction Supervision
• QA/QC
• Conceptual Design
• Project Management
• Programme Management
• Detailed Design
• Construction Management
• Project Commissioning
BAYAN BARU SEWER NETWORK PROJECT (PHASE 2), PENANG
Bayan Baru Sewer Network Phase 2 is designed for 650,000 PE. During preliminary stage, 14 sewer lines have been proposed and approved. However, based on the outcome from the Value Management which has taken into consideration of financial allocation for this project by the Government, only 5 lines were chosen and the pipe diameter ranged from 225mm to 1,800mm.
LOCATION
Penang
CLIENT
Jabatan Perkhidmatan Pembetungan
COMPLETION DATE
2007
DETAIL WORKS INCLUDED
• Construction of 5 main sewer lines
• Network pumping station NPS 1 of 8,600PE capacity
• Upgrading of existing NPS 2 from 40,000PE to 70,000PE
• Rationalisation of the existing 11 numbers of public plants
SERVICES PROVIDED
• Planning and Detailed Design
• Construction Supervision
• Contract Administration
PEMBINAAN LOJI RAWATAN KUMBAHAN SERANTAU DAN RANGKAIAN PAIP PEMBETUNGAN DI BANDAR KUANTAN, PAHANG (REKA DAN BINA)
LOCATION
Bandar Kuantan, Pahang
CLIENT
Jalur Cahaya Sdn Bhd
COMPLETION DATE
Current
DETAIL WORKS INCLUDED
• 68km sewer (gravity pipe and force main)
• Major crossing of 350m wide Kuantan River
• Rationalisation of 165 nos. public and private STPs
• Sewer pipe size: 225mm to 1,650mm diameter, max. depth of 15m
• Detailed Design of Sewerage conveyance System with Catchment Area (total 172.6 km2)
SERVICES PROVIDED
• Planning and Detailed Design
• Contract Administration
• Design Review
• Construction Supervision
Integrated Management System
&
Quality Policy
MS ISO 9001:2015 Quality Management Systems
MS ISO 14001:2015 Environmental Management System
MS ISO 45001:2018 Occupational Health and Safety Management System